From the beginning of 4th quarter of 2008 to now, many large-scale construction projects such as ports, roads, over bridges crossing the river by the Ministry of Traffic & Transportation (MOTT) as an investor , is done in the form of international competitive bidding was not able to find contractors.
Specifically, two construction packages build path north and south of the Nhat Tan construction project (Hanoi), there was only one contractor submitted bids;
PK1 Package, new project of building Highway 3 -the road of Ha Noi - Thai Nguyen, the lowest contractor's bid exceeded 2,000 billion dong compared to the package price;
6b Package "embellish beach, build underwater of embankments, piers and retaining wall in the station", The Van Phong port construction project was only one bidder submitted bids, with bid prices exceeded 1,272 billion dong compared with the package price.
The estimated package built on out-of-dated cost inputs, concerns about delaying in land level clearance were reasons making international contractors turned his back on above packages that have been evaluated high appeal.